NEW QUESTION # 16
In the Product Cost by Order process, what does the system calculate depending on the order status?
- A. Both WIP and variances
- B. WIP at target costs or variances
- C. WIP at percentage of completion (PoC) method or variances
- D. WIP at actual costs or variances
Answer: D
NEW QUESTION # 17
Which of the following steps are part of the procedure to update the standard price of the material? Note:
There are 2 correct answers to this question.
- A. Mark the cost estimate.
- B. Release the cost estimate.
- C. Archive the cost estimates.
- D. Split the costs.
Answer: A,B
NEW QUESTION # 18
How do you maintain number range intervals in Controlling?
- A. By document type
- B. By cost element category
- C. By business transactions
- D. By account type
Answer: C
NEW QUESTION # 19
What are some of the characteristics of planning for internal orders? Note: There are 2 correct answers to this question.
- A. Availability control can check against plan values.
- B. You can plan multiple versions.
- C. You can define tolerance limits for plan overspend.
- D. You can enter costs and revenues.
Answer: B,D
NEW QUESTION # 20
At which level do you define the valuation method for results analysis?
- A. Operating concern
- B. Controlling area
- C. Company code
- D. Plant
Answer: B
NEW QUESTION # 21
For which of the following situations would you need to implement the transfer price solution in SAP S4/NANA?
- A. Parallel variation views of the same logistical flows are needed to differentiate between legal and profit center valuation.
- B. Parallel price calculation and invoicing are needed to facilitate intercompany reconciliation.
- C. Parallel accounting is needed in order to be compliant with different accounting principles.
- D. Parallel costing is needed in order to calculate separate costs of goods manufactured for different accounting principles.
Answer: A
NEW QUESTION # 22
You want to maintain a cost component structure. What can you determine for each cost component? Note:
There are 3 correct answers to this question.
- A. Relevance of cost component to results analysis
- B. Assignment of cost component to calculation base for overheads in costing sheet
- C. Relevance of cost component to goods manufactured
- D. Assignment of cost component of cost component group
- E. Relevance of cost component to inventory valuation
Answer: C,D,E
NEW QUESTION # 23
You want to use template to consider overhead during product costing. How do you assign the template to your material?
- A. Using an origin group and an overhead group
- B. Using a special procurement type and an overhead group
- C. Using a profit center and an overhead key
- D. Using an overhead group and an overhead key
Answer: D
NEW QUESTION # 24
You are setting up costing-based Profitability Analysis for your organization. How do you configure the deferent market segments?
- A. As value fields
- B. As divisions
- C. As key Figures
- D. As characteristics
Answer: D
NEW QUESTION # 25
What do you need to setup in order to bring the values incoming sales orders into account-based Profitability Analysis?
- A. A new standard G/L ledger with exclusive usage of "Prediction"
- B. An extension ledger of type "Simulation"
- C. A multi-valuation ledger
- D. An extension ledger of type "Prediction and Commitment"
Answer: D
NEW QUESTION # 26
You have implemented Product Cost by Sales Oder in conjunction with revenue-based results analysis in your organization.
For a particular sales order item, you have the following:
Plan revenue = 3000; Plan costs = 2000
Actual revenue = 1200; Actual costs = 1000
What data does the system calculate during results analysis?
- A. Revenue = 1200; Cost of sales = 800; Reserve = 200
- B. Revenue = 1200; Cost of sales = 1000; WIP = 200
- C. Revenue = 1200; Cost of sales = 800; WIP = 200
- D. Revenue = 1200; Cost of sales = 1000; Reserve = 200
Answer: C
NEW QUESTION # 27
At what level do you create the structure of the operating concern?
- A. Sales organization level
- B. Controlling area level
- C. Company code level
- D. Client level
Answer: D
NEW QUESTION # 28
Which receiver must be allowed in the settlement profile of product cost collector?
- A. Order
- B. Material
- C. Cost center
- D. G/L Account
Answer: B
NEW QUESTION # 29
How does SAP S/4HANA determine if a characteristic value is valid in Profitability Analysis?
- A. By defining the characteristic value in the check table
- B. By defining the characteristic value as a value field
- C. By defining the characteristic value as a key figure
- D. By defining the characteristic value in the field catalog
Answer: A
NEW QUESTION # 30
You have implemented Product Cost by Sales Oder in conjunction with cost-based POC results analysis in your organization.
For a particular sales order item, you have the following:
Plan revenue = 3000; Plan costs = 2000
Actual revenue = 1200; Actual cost=1000
What data does the system calculate during results analysis?
- A. "Revenue = 1200; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 200"
- B. "Revenue = 1200; Cost of sales = 1000; Revenue surplus =200"
- C. "Revenue = 1500; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 300"
- D. "Revenue = 1500; Cost of sales = 1000; Revenue surplus =300"
Answer: C
NEW QUESTION # 31
You are running an indirect activity allocation. What do you post to the sender and receiver?
- A. You post both quantity and cost to the receiver, and cost only to the sender.
- B. You post only cost to both the sender and receiver.
- C. You post both quantity and cost to the sender, and cost only to the receiver.
- D. You post quantity and cost to both the sender and receiver.
Answer: D
NEW QUESTION # 32
In which module do you process profit center allocations in SAP S/4HANA?
- A. Product cost accounting
- B. General ledger accounting
- C. Account-based profitability analysis
- D. Cost center accounting
Answer: B
NEW QUESTION # 33
How does the system derive the requirement type from the material master data? Note: There are 2 correct answers to this question.
- A. MRP group -> requirements class -> planning strategy -> requirements type
- B. Strategy group -> planning strategy -> requirements class -> requirements type
- C. Strategy group -> planning strategy -> requirements type
- D. MRP group -> Strategy group -> planning strategy -> requirements type
Answer: C,D
NEW QUESTION # 34
......
Prepare For The C_TS4CO_2021 Question Papers In Advance: https://www.prepawaytest.com/SAP/C_TS4CO_2021-practice-exam-dumps.html