NEW QUESTION 30
What is the correct task status flow for a Review task?
- A. Not started -> In Process -> Reviewed
- B. Not started -> In Review -> Complete
- C. Not started -> In Review -> Reviewed
- D. Not started -> Reviewed -> Complete
Answer: B
Explanation:
https://docs.oracle.com/en/cloud/saas/human-resources/20d/faupf/submit-and-monitor- flows.html#FAUPF3755929
NEW QUESTION 31
You need to create contract workspaces using the legacy load process. Which CSV file must the customer populate?
- A. Contracts.csv
- B. ContractDocuments.csv
- C. ContractLoad.csv
- D. ContractTeam.csv
Answer: B
Explanation:
https://help.sap.com/viewer/bf48a3e8cc664aa199257a55376830f3/cloud/en-
US/7c0483c571ea10148bc8b446cedc14cd.html
NEW QUESTION 32
What are the benefits of SAP Ariba Sourcing integration with Ariba Contract Management? Note: There are 2 correct answers to this question
- A. Allows contract workspace information to be used to select the winning supplier in the sourcing event
- B. Streamlines the flow of information from the contract workspace into the sourcing event
- C. Expedites the creation of a contract workspace after a sourcing event is awarded (Missed)
- D. Automatically populates information from a sourcing event into the contract workspace (Missed)
Answer: B,D
Explanation:
https://www.tutorialspoint.com/sap_ariba/sap_ariba_quick_guide.htm
NEW QUESTION 33
What benefit does your customer have when they include documents in the Contract Workspace template?
- A. Documents inherited from the template into the contract workspace can be edited or deleted
- B. Documents that are added to project templates are included in all contract workspaces created using that template
- C. Conditions on documents can be copied from the template but can also be created in the individual contract workspace
- D. A user can create contract workspaces from a Sourcing Project template to copy the sourcing documents into that contract workspace
Answer: B
NEW QUESTION 34
For which of the following contract documents can you set up document properties? Note: There are 2 correct answers to this question
- A. Contract Addendum (Missed)
- B. Main Agreement (Missed)
- C. Pricing Terms
- D. Supplier Paper
Answer: A,B
Explanation:
https://help.sap.com/viewer/4ca0f94a06f24fadb67b16f18c3e742d/cloud/en-
US/ad5002531fa245d9ba934e595752b3ca.html
NEW QUESTION 35
Your customer needs to organize their users permissions within SAP Ariba according to their business roles. What action do you perform?
- A. Create custom groups that are listed as children of the appropriate system groups
- B. Add users to the appropriate project groups within a project or workspace
- C. Create several master users and delegate their authority to other users in the system
- D. Use the Import Enterprise Users task to load a Microsoft Excel spreadsheet containing user data
Answer: B
Explanation:
https://connect.ariba.com/CCO_Forums/buyer_config.pdf
NEW QUESTION 36
What benefit does your customer have by using the contract template? Note: There are 2 correct answers to this question
- A. Template items can be deleted in projects
- B. New header fields can be created
- C. Standardized workflow is applied to all workspaces (Missed)
- D. Workspace content can be re-used (Missed)
Answer: C,D
NEW QUESTION 37
What document is created when you export a contract workspace to SAP ERP?
- A. Operational contract
- B. Purchase order
- C. Scheduling agreement
- D. Framework agreement
Answer: D
Explanation:
https://en.wikipedia.org/wiki/Framework_agreement#:~:text=In%20the%20context%20of%20procurem ent,appropriate%2C%20the%20quantity%20envisaged%22.
NEW QUESTION 38
What is SAP Ariba's best practice for contracts documents that contain similar text in the clauses?
- A. Use a condition to insert the right clause into the document when the workspace is created
- B. Clauses for documents should NOT be changed because they were approved by the legal department
- C. Whenever possible, reword similar clauses to create a standard clause used in multiple agreements
- D. Decide on the best constructed clause and use the other clauses as alternate or fallback clauses
Answer: B
NEW QUESTION 39
What benefits do project groups offer? Note: There are 3 correct answers to this question
- A. Visibility to projects and workspaces when access control is in place (Missed)
- B. Ability to reuse project groups in any future projects
- C. Option to add e-mail reviewers to an approval process
- D. Assignment of user permissions that are specific to a single project or workspace (Missed)
- E. Automatic assignment of users to the Team tab of a project or workspace (Missed)
Answer: A,B,E
NEW QUESTION 40
Your customer has integrated Ariba Contract Management and Ariba Contract Compliance. How do you modify the contract compliance terms?
- A. 1. Create a termination-type amendment to the contract workspace
2. Close the contract terms
3. Create and submit a new contract terms file - B. 1. Access the published contract request
2. Update the contract request
3. Submit the changes for approval - C. 1. Create an amendment-type amendment to the contract workspace
2. Update the contract terms
3. Publish the contract workspace - D. 1. Create an administrative-type amendment to the contract workspace
2. Update the contract terms
3. Publish the contract workspace
Answer: C
NEW QUESTION 41
Which of the following activities are recommended before you upload the Main Agreement? Note:
There are 3 correct answers to this question
- A. Set the document properties
- B. Create styles in Microsoft Word (Missed)
- C. Complete document cleansing (Missed)
- D. Bookmark the document (Missed)
- E. Add conditions to the document
Answer: C,D,E
NEW QUESTION 42
Which bookmark type includes the paragraph mark?
- A. Clause
- B. Sub-Section
- C. Section
- D. Sub-Clause
Answer: C
Explanation:
https://makeofficework.com/bookmarks_the_basics.htm
NEW QUESTION 43
Which documents must you create to transfer bid data from Ariba Sourcing to a contract workspace?
Note: There are 2 correct answers to this question
- A. Purchase order
- B. Scenario (Missed)
- C. Award (Missed)
- D. Bid report
Answer: C,D
Explanation:
https://aribasourcing.weebly.com/working-with-documents
NEW QUESTION 44
Which amendment type do you use if your customer only needs to change the team members?
- A. Renewal amendment
- B. Termination amendment
- C. Amendment amendment
- D. Administrative amendment
Answer: A
Explanation:
https://www.contractexperience.com/resources/contract-amendment.html
NEW QUESTION 45
What is the SAP Ariba best practice for managing contract workspace templates?
- A. Export templates so that changes can be made more quickly using Microsoft Excel and a text editor
- B. Create templates in parallel so that settings can be compared during the configuration process
- C. Enable Template Upgrade so that existing contracts are upgraded when they are amended
- D. Create an initial template and receive business approval so that it can copied as the basis for additional templates
Answer: D
NEW QUESTION 46
You are setting up a number of contracts with different suppliers to work on a facilities construction project. How would you create the new workspaces to link them to each other in the system?
- A. Create follow-on projects
- B. Copy the project
- C. Create sub-agreements
- D. Create a sub-project
Answer: A
NEW QUESTION 47
What must you check when you import templates from one Contract Management realm to another?
Note: There are 2 correct answers to this question
- A. The Process template must be in Published status
- B. The Contract Management solution must be of the same version and service pack (Missed)
- C. Both instances must share the same master data (Missed)
- D. The documents must all be published
Answer: B,C
NEW QUESTION 48
......