NEW QUESTION 51
Which is a purpose of the plans theme?

  • A. To understand whether the targets are achievable
  • B. To assess and control uncertainty
  • C. To establish the project's structure of accountability
  • D. To identify, assess and control any potential changes to the baseline

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Plans

 

NEW QUESTION 52
How many management stages should a PRINCE2 project consist of?

  • A. Initiation stage and at least one other management stage to cover the remainder of the project
  • B. Start up stage, initiation stage and a closing stage
  • C. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
  • D. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project

Answer: A

 

NEW QUESTION 53
Which is shown in a product breakdown structure?

  • A. What resources are required to develop the products
  • B. Management stages, major products and control points
  • C. The major products that are to be developed in a plan
  • D. In which order the products should be created

Answer: C

 

NEW QUESTION 54
Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.

  • A. are able to overturn the decisions of
  • B. should support
  • C. must be accountable to
  • D. report to the project board and

Answer: B

 

NEW QUESTION 55
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.

  • A. when a stage plan has been prepared for
  • B. at, or close to the end of,
  • C. when all the delivery steps have been completed within
  • D. at the beginning of

Answer: B

Explanation:
Explanation
Reference
https://publications.axelos.com/Prince2Agile2015/content.aspx?showNav=true&expandNav=true&page=cros_13

 

NEW QUESTION 56
According to the 'continued business justification' principle, what should happen to the funds when a project can no longer be justified?

  • A. They should be used to deliver a reduction in the scope of the project
  • B. They should be used to create an alternative business case for the project
  • C. They should be returned to corporate, programme management or customer
  • D. They should be transferred back to the project board to reassign

Answer: C

 

NEW QUESTION 57
Which is a minimum requirement for applying the risk theme?

  • A. Threats must be assessed for their impact on the viability of the project
  • B. The PRINCE2 risk management procedure must be followed
  • C. Team managers must maintain their own risk registers
  • D. A single role that is responsible for all risks must be defined

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-2017-risk-theme-changes/

 

NEW QUESTION 58
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

  • A. When an organization produces its business plans
  • B. Before work to start the project commences
  • C. When authorized by the corporate, programme management or the customer
  • D. After the executive has been appointed

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Continued_business_justification

 

NEW QUESTION 59
Which is a purpose of the change theme?

  • A. To identify, assess and control any potential and approved changes to baselined products
  • B. To assess and control uncertainty
  • C. To prevent change to baselined products
  • D. To establish mechanisms to monitor and compare actual achievements against those planned

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-prince2-change- theme

 

NEW QUESTION 60
Why is it necessary to apply the 'defined roles and responsibilities' principle?

  • A. Because the project management team should be cross-functional
  • B. Because the user and supplier interests should be involved on a need-to-know basis
  • C. Because the project manager should represent all the stakeholders of the project
  • D. Because the people involved in a project should know what is expected of them

Answer: D

Explanation:
Section: Volume B

 

NEW QUESTION 61
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes,
[ ? ] and tailoring PRINCE2 to the project environment.

  • A. products
  • B. activities
  • C. quality
  • D. processes

Answer: D

Explanation:
Explanation/Reference:
Reference http://www.innolead.co.bw/index.php/inno-content/cid/27/prince2/

 

NEW QUESTION 62
Which role is responsible for creating Checkpoint Reports?

  • A. Team Manager
  • B. Senior Supplier
  • C. Project Support
  • D. Change Authority

Answer: A

 

NEW QUESTION 63
Which is a purpose of the Controlling a Stage process?

  • A. Produce a Team Plan for the work to be assigned to a Team Manager
  • B. Select and implement actions that will resolve deviations from a plan within tolerance
  • C. Obtain approvals for products delivered in a Work Package
  • D. Update a Project Plan to incorporate the actuals from a Stage Plan

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 64
Which is NOT a purpose of a Benefits Review Plan?

  • A. Describe how to measure and confirm any benefits that are to be realised after the project is closed
  • B. Define the scope, timing and ownership of the benefit reviews required
  • C. Define the period over which the cost-benefit analysis will be based
  • D. Describe how to measure the performance of the project's products in operational use

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 65
Which is NOT a purpose of the Initiating a Project process?

  • A. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
  • B. Enable the Project Board to decide whether it is worthwhile to initiate a project
  • C. Enable a Project Board decision about the commitment of resources to a project
  • D. Establish solid foundations for a project

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 66
Which is a minimum requirement when applying the business case theme?

  • A. To specify the solution to be used to deliver the business option selected
  • B. To ensure the corporate business plan is updated with the project costs and benefits
  • C. To integrate the benefits management approach with the project and stage plans
  • D. To define the management actions required to ensure the project's outcomes are achieved

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 67
What is a goal of the 'implement' step within the recommended risk management procedure?

  • A. To estimate the risk to the project in terms of probability and impact
  • B. To monitor the effectiveness of actioned risk responses
  • C. To communicate information related to the risks faced by the project
  • D. To prepare specific management responses to identified risks

Answer: A

 

NEW QUESTION 68
In what product should the quality criteria for a specialist product be recorded?

  • A. Quality Management Strategy
  • B. Product Description
  • C. Quality Register
  • D. Project Product Description

Answer: B

 

NEW QUESTION 69
Identify the missing word in the following sentence, A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.

  • A. issues
  • B. costs
  • C. benefits
  • D. risks

Answer: C

 

NEW QUESTION 70
Which is a purpose of an End Project Report?

  • A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  • B. Identify individuals or groups that need to be told that the project is coming to an end
  • C. Review how well the project performed against the Project Initiation Documentation used to authorize it
  • D. Ensure that key project information is archived and made secure

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 71
Which is a responsibility of the project board?

  • A. To ensure production of the project's outputs
  • B. To implement the change control approach
  • C. To manage the team managers and project support
  • D. To ensure effective communication with external stakeholders

Answer: D

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Organization#Project_Board

 

NEW QUESTION 72
Who does the Team Manager report to and take direction from?

  • A. Project Manager
  • B. Project Assurance
  • C. Project Support
  • D. Project Board

Answer: A

 

NEW QUESTION 73
Which statement describes the responsibilities of a risk actionee?

  • A. Managing, monitoring and controlling of all aspects of an assigned risk
  • B. Owning and authorizing the use of the risk budget to fund risk responses
  • C. Carrying out a risk response action to respond to a particular risk
  • D. Identifying risks to the project that might occur in their department

Answer: C

 

NEW QUESTION 74
Which product identifies how often stakeholders require information?

  • A. Benefits management approach
  • B. Configuration item record
  • C. Communication management approach
  • D. Lessons report

Answer: C

 

NEW QUESTION 75
Which statement about applying the 'tailor to suit the project' principle is CORRECT?

  • A. A technically complex project should NOT tailor PRINCE2
  • B. PRINCE2 can be tailored to be used with any type of project
  • C. The tailoring of PRINCE2 is MOST appropriate for agile projects
  • D. A project which is part of a programme should NOT tailor PRINCE2

Answer: B

Explanation:
Reference: http://prince2.wiki/Tailoring

 

NEW QUESTION 76
......

Focus on PRINCE2Foundation All-in-One Exam Guide For Quick Preparation: https://www.prepawaytest.com/PRINCE2/PRINCE2Foundation-practice-exam-dumps.html

PRINCE2Foundation All-in-One Exam Guide For Quick Preparation: https://drive.google.com/open?id=1bXfc7ULrMno4J5P-3B1m5JSfJ0riFhnc

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 )
From Monday to Saturday

Support: Contact now