NEW QUESTION 15
In which phase should you first run the SAP Readiness Check for SAP S/4HANA in a "Selective Data Transition" transition path, in a System Consolidation scenario that includes conversion from SAP ERP?
Please choose the correct answer.
Response:
- A. Discover
- B. Explore
- C. Prepare
- D. Realize
Answer: A
NEW QUESTION 16
Which of the following tools is used to install SAP S/4HANA.
Please choose the correct answer.
Response:
- A. Data Migration server
- B. Cloud Application Library
- C. SAP Solution Manager
- D. SWPM (Software Provisioning Manager)
Answer: D
NEW QUESTION 17
Which activities are critical for delivering Agile projects?
There are 2 correct answers to this question.
Response:
- A. Release planning
- B. Blueprint scheduling
- C. Retrospective agenda creation
- D. Sprint planning
Answer: A,D
NEW QUESTION 18
Which activity helps the Project Team add User Stories to the Product Backlog?
- A. Conducting the Solution Validation workshop
- B. Preparing a project schedule
- C. Assessing project risks
- D. Planning the User Acceptance Test
Answer: A
NEW QUESTION 19
What does the Side-by-Side Extensibility Option mean?
Please choose the correct answer.
Response:
- A. Context-aware SAP S/4HANA extensions, focused on tight integration
- B. Extensibility based on the SAP Cloud Platform and published APls
- C. Have two SAP S/4HANA instances - one for standard code, and another for custom developments
- D. Transfer reporting to BW/4HANA
Answer: B
NEW QUESTION 20
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud?
Please choose the correct answer.
Response:
- A. SAP Transformation Navigator
- B. Implementation portal for SAP S/4HANA Cloud
- C. SAP Support Marketplace
- D. SAP Roadmap Viewer
Answer: B
NEW QUESTION 21
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:
- A. Explore
- B. Prepare
- C. Realize
- D. Deploy
Answer: A
NEW QUESTION 22
What is the basis for approving work results (signing Act of Acceptance) on a Project Phase level?
Please choose the correct answer.
Response:
- A. Definition of Done for User Story
- B. Agreed and met Acceptance Criteria within Quality Gate
- C. Scrum of Scrums meeting decision
- D. Definition of Ready for Sprint
Answer: B
NEW QUESTION 23
Which end-to-end turn-key Application Lifecycle Management (ALM) solution can support you in managing requirements and software development for large, Agile projects?
Please choose the correct answer.
Response:
- A. Solution Manager Test Suite
- B. Focused Build
- C. Requirement Management
- D. Change Request Management
Answer: B
NEW QUESTION 24
What term is used for a Ready-to-run SAP S/4HANA system with pre-built Solution Documentation, which supports End-to-End Processes for a specific industry so that the Project Team can focus on differentiation and innovation?
Please choose the correct answer.
Response:
- A. Fully Activated Appliance
- B. Best Practice System
- C. SAP Cloud Appliance Library
- D. SAP Model Company
Answer: D
NEW QUESTION 25
In what respect is SAP Activate Methodology different from the ASAP Methodology?
Please choose the correct answer.
Response:
- A. Leverages iterative incremental build
- B. Supports cloud deployments
- C. Includes Fit/Gap analysis instead of Blueprint
- D. Supports only new implementations
Answer: C
NEW QUESTION 26
What accelerator can help you document the configuration definition in the explore Phase?
- A. Change request template
- B. Data definition
- C. Test strategy
- D. Backlog template
Answer: D
NEW QUESTION 27
Which estimation technique can be used in to size the User Stories during Sprint Planning?
Please choose the correct answer.
Response:
- A. Product Owner's relative estimate of the effort that will be needed to implement the User Story
- B. Detailed bottom-up effort estimate by the Scrum Master in Story Points based on the User Story complexity
- C. Detailed bottom-up effort estimate that breaks each User Story up into hours or shorter tasks
- D. Relative estimate in Ideal Person Days that reflects the best estimate provided by the project team
Answer: A
NEW QUESTION 28
Which of the following belong to the Application Design and Configuration work stream for SAP S/4HANA Cloud in the Explore phase?
There are 2 correct answers to this question.
Response:
- A. Integration prerequisites confirmation
- B. Configuration definition
- C. Kick-off workshop
- D. Fit-to-standard workshop
Answer: B,D
NEW QUESTION 29
What is the term used for workshops, which are intended to set value targets, validate SAP Standard functionality against customer requirements.
And collect delta requirements in the "New Implementation of SAP S/4HANA" transition path?
Please choose the correct answer.
Response:
- A. Delta Design
- B. Solution Validation
- C. Fit-to-Standard
- D. Design Thinking
Answer: B
NEW QUESTION 30
How are the build and test tasks planned and executed in the Realize phase?
Please choose the correct answer.
Response:
- A. By executing regression tests after each iteration
- B. With Q-Gates for sign off after each iteration
- C. By using incremental build in fixed-scope iteration
- D. By using the sprint backlog list as input for each iteration.
Answer: C
NEW QUESTION 31
What are two important approaches, based on the control centre concept, that SAP Proposes to use for streamlined implementation and operations?
There are 2 correct answers to this question
- A. Run SAP like a factory
- B. Intelligent enterprise
- C. Always connected
- D. Build SAP like a factory
Answer: A,D
NEW QUESTION 32
Ready-to-use Content in SAP Activate includes which of the following?
There are 2 correct answers to this question.
Response:
- A. Courses delivered by SAP Education
- B. SAP Best Practices
- C. Project Accelerators
- D. Business models from leading companies in each industry sector
Answer: B,C
NEW QUESTION 33
Which of the following are part of the 10 SAP quality principle?
There are 2 correct answers to this question
- A. Start scoping early
- B. Achieve production readiness
- C. Plan phase at a time
- D. Use standard functionality optionally
Answer: A,B
NEW QUESTION 34
In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the customer?
Please choose the correct answer.
Response:
- A. Explore
- B. Prepare
- C. Realize
- D. Deploy
Answer: A
NEW QUESTION 35
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
- A. Before Integration Testing
- B. After Integration Testing
- C. During each Firm-up Sprint
- D. After each Sprint
Answer: B
NEW QUESTION 36
What information does the product team need so that they can estimate the relative size of backlog user story correctly?
Please choose the correct answer.
Response:
- A. Overall project schedule
- B. Available project resources
- C. Definition of Done
- D. Test strategy
Answer: C
NEW QUESTION 37
Which Value Chains does SAP Solution Manager 7.2 deliver? Note:There are 3 correct answers to this question.
- A. Hire-to-Retire
- B. Detect-to-Correct
- C. Cash-to-Order
- D. Request-to-Fulfill
- E. Requirements-to-Deploy
Answer: B,D,E
NEW QUESTION 38
......
C_ACTIVATE13 Dumps To Pass SAP Exam in 24 Hours - PrepAwayTest: https://www.prepawaytest.com/SAP/C_ACTIVATE13-practice-exam-dumps.html