ASIS PSP Certification Exam covers a range of topics related to physical security, including security principles and practices, physical security assessments, security system design, and emergency response planning. Candidates must demonstrate a thorough understanding of these topics through a rigorous exam that tests their knowledge, skills, and experience. ASIS Physical Security Professional Exam certification is valid for three years and requires ongoing professional development to maintain. Overall, the ASIS PSP Certification Exam is an essential certification for professionals in the field of physical security and offers a valuable opportunity for career advancement and professional growth.

 

NEW QUESTION # 59
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

  • A. 368 CM
  • B. 263 CY
  • C. 201 CY
  • D. 306 CY

Answer: D


NEW QUESTION # 60
The division of several area programmed supervision results in a aggregate operational audit, and aggregate operational audit considered in aggregate are an entire company's programmed supervision.

  • A. True
  • B. False

Answer: B


NEW QUESTION # 61
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

  • A. 03-21-04
  • B. 02-19-04
  • C. 03-11-04
  • D. 03-20-04

Answer: C


NEW QUESTION # 62
A hybrid system is a combination of:

  • A. Security consultants & services
  • B. Proprietary & Contract security
  • C. Standard & Security acts
  • D. Security & Control

Answer: B


NEW QUESTION # 63
What problems can a soils engineer deal with on a project?

  • A. Archeological findings.
  • B. Survey error.
  • C. Toxic soils.
  • D. Hidden subsurface conditions.

Answer: D


NEW QUESTION # 64
Which alarm warn of a process reaching a dangerous temperature, of the presence of toxic fumes, or that a machine is running too fast?

  • A. Burglar alarm
  • B. Intrusion alarms
  • C. Protection alarm
  • D. Special-use alarm

Answer: B


NEW QUESTION # 65
The process of ensuring that the information is not manipulated in an unauthorized way or corrupted, thus diminishing its value and utility to the organization is called:

  • A. Security
  • B. Integrity
  • C. Analysis
  • D. Availability

Answer: B


NEW QUESTION # 66
Theft triangle consists of:

  • A. motive, desire, opportunity
  • B. dishonesty, financial problem, prospect
  • C. motive, condition, opportunity
  • D. dander, desire, opportunity

Answer: A


NEW QUESTION # 67
A good risk management program involves:

  • A. Identify risks or specific vulnerabilities
  • B. Analyze and study risks, including likelihood and degree of danger of an event
  • C. All of the above
  • D. Study of security programs

Answer: C


NEW QUESTION # 68
What problems can a soils engineer deal with on a project?

  • A. Archeological findings.
  • B. Survey error.
  • C. Toxic soils.
  • D. Hidden subsurface conditions.

Answer: D

Explanation:
Role of Soils Engineer:
* Soils engineers address subsurface conditions, such as soil stability, unexpected geology, and underground obstacles.
Evaluation of Other Options:
* A: Survey errors are typically addressed by surveyors.
* C: Archeological findings involve specialists in historical preservation.
* D: Toxic soils are typically handled by environmental engineers.
Verification with PSP Guidelines:The PSP Study Guide includes subsurface investigations as a key responsibility for geotechnical professionals (Ref: PSP Study Guide, Chapter 1A: Site Conditions).


NEW QUESTION # 69
If all other work proceeds according to the Baseline plan, how many times will the critical path change?

  • A. Does not change.
  • B. 3.
  • C. 2.
  • D. 1.

Answer: A


NEW QUESTION # 70
The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

  • A. uses arrows to signify logic in a network
  • B. allows multiple relationship types to be associated with activities
  • C. allows more than one critical path to be represented
  • D. can be used to calculate the late start and late finish of all activities

Answer: A


NEW QUESTION # 71
SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?

  • A. SUBCO direct labor and equipment rates
  • B. BILCO liquidated damages in the SDOT contract
  • C. The distance of SUBCO to your project
  • D. Pending negotiations with GOUGE.

Answer: A


NEW QUESTION # 72
Which approach is dealt with terrorists' personalities, their recruitment, and their induction into terrorist organizations, beliefs, attitudes, motivations and careers?

  • A. Physiological Approach
  • B. Criminal approach
  • C. Violence Approach
  • D. Multifactor Approach

Answer: A


NEW QUESTION # 73
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Expedite packaging by 5 days.
  • B. Expedite printing by 5 days.
  • C. Delay product release by 5 days.
  • D. Delay manufacturing by 5 days.

Answer: B

Explanation:
Situation Analysis:
* Proofing of the product manual requires 15 additional days.
* This impacts the Print Product Manual (Activity F), which is a critical path activity.
Maintaining the Availability Date:
* To prevent delays in the product release (Activity H), the additional 15 days for proofing must be offset.
* Reducing the printing duration (Activity F) by 5 days ensures the schedule stays on track.
* Expediting other activities like manufacturing or packaging would not directly compensate for the proofing delay.
Cross-Verification:
* Option A: Incorrect. Delaying product release impacts availability.
* Option B: Incorrect. Packaging is not a direct predecessor of the product release.
* Option D: Incorrect. Delaying manufacturing has no impact on proofing.
* Option C: Correct. Expedites the critical path by compensating for the delay.


NEW QUESTION # 74
If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

  • A. Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.
  • B. Reduce the duration of B" from 10 days to 5 days by compressing work effort
  • C. Replace the relationship from 'B' to 'C' with SSO

Answer: A

Explanation:
Understanding the Problem Context:
* Activity C is currently set to complete on Day 40.
* Activity A has a 5-day delay in starting, so adjustments are needed to maintain the Day 40 completion date for Activity C.
* The key is to identify which adjustment will fail to maintain the timeline.
Option-by-Option Analysis:
* A. Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from 'B' to 'C' with FSO (Finish-to-Start with Offset):
* Reducing Activity A's duration from 20 to 10 days might mitigate part of the delay, but replacing the relationship between B and C with FSO introduces an offset.
* FSO relationships typically delay the start of successor activities (Activity C in this case).
* This would likely push Activity C beyond Day 40 because the delay in B's finish, coupled with the offset, would result in C starting later.
* This adjustment does NOT maintain the completion date of Activity C.
* B. Replace the relationship from 'B' to 'C' with SSO (Start-to-Start with Offset):
* An SSO relationship allows Activity C to begin once Activity B starts (with or without an offset).
* This adjustment effectively overlaps the schedules of B and C, mitigating delays from A.
* This adjustment can maintain the completion date of Activity C at Day 40.
* C. Reduce the duration of 'B' from 10 days to 5 days by compressing work effort:
* Reducing B's duration by compressing its schedule shortens its timeline, allowing Activity C to start sooner.
* This adjustment offsets the delay caused by Activity A.
* This adjustment can maintain the completion date of Activity C at Day 40.
Final Answer and Justification:
* The adjustment described in A will NOT maintain the completion date of Activity C at Day 40 because the FSO relationship introduces delays, making it ineffective in this scenario.
* Options B and C offer feasible adjustments to maintain the timeline.
Study Guide Reference:
* Refer to the PSP Certification Study Guide, Chapter 2 - Scheduling, Subchapter 2.2.4: Relationships (p. 151-157), which details the impact of logical relationships (FSO, SSO) on schedule timelines.
* Additionally, review AACE Recommended Practice 52R-06: Time Impact Analysis for insights into how delays affect dependent activities and methods for mitigating them.


NEW QUESTION # 75
Which of the following will always describe the critical path? The path with

  • A. Zero float.
  • B. The longest duration through the network.
  • C. The shortest duration and negative float.
  • D. Negative float.

Answer: A


NEW QUESTION # 76
What day would Activity C complete if the duration of Activity A was reduced by five days?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: B


NEW QUESTION # 77
How much Total Float does drafting the product manual have?

  • A. 15 workdays.
  • B. 5 workdays.
  • C. 10 workdays.
  • D. 0 workdays.

Answer: C


NEW QUESTION # 78
......

ASIS PSP Test Engine PDF - All Free Dumps: https://www.prepawaytest.com/ASIS/PSP-practice-exam-dumps.html

Get New PSP Certification – Valid Exam Dumps Questions: https://drive.google.com/open?id=1415nFY5zGpaWveEG2pX8OGRp9QQhIqwf

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 )
From Monday to Saturday

Support: Contact now